Man Hours versus Time S-curve
The Man Hours versus Time S-curve is appropriate for
projects that are labor intensive. It shows cumulative man hours
expended over time for the duration of the project. As man-hours are a
product of manpower and working hours, these may be adjusted together or
individually in an attempt to keep the project on schedule. Projects
may require additional man-hours to finish on time due to low
productivity, delays and disruptions, rework, variations, etc.
Costs versus Time S-curve
The Costs versus Time S-curve is appropriate for projects that
contain labor and non-labor (e.g. material supply / hire / subcontract)
tasks. It shows cumulative costs expended over time for the duration of
the project, and may be used to assist in the calculation of the
project's cash flow, and cost to complete.
Baseline S-curve
Prior to project commencement, a schedule is prepared outlining the
proposed allocation of resources and the timing of tasks necessary to
complete the project within a set time frame and budget. This schedule
is referred to as the Baseline Schedule. From this schedule, a Baseline
S-curve is generated. This S-curve reflects the planned progress of the
project. If the project requirements change prior to commencement (e.g.
change of scope, delayed start), the Baseline Schedule may require
revision to reflect the changed requirements.
Target S-curve
Following project commencement, modification of the Baseline Schedule
is usually required. Changes are continually made to the Production
Schedule (which is originally the same as the Baseline Schedule). The
production schedule reflects the actual progress of the project to date,
and any revisions made to tasks yet to commence or not yet completed.
From this schedule, a Target S-curve may be generated. This S-curve
reflects the ideal progress of the project if all tasks are completed as
currently scheduled. In an ideal world, the Target S-curve will meet
the Baseline S-curve at the end of the project (On Time, On Budget) or
finish below and to the left of the Baseline S-curve (Early, Under
Budget). In reality, it is not uncommon for the Target S-curve to finish
above and to the right of the Baseline S-curve (Late, Over Budget).
Actual S-curve
The production schedule is updated on a regular basis throughout the
duration of the project. These updates include the revision of
percentage complete for each task to date. Using this information, an
Actual S-curve may be generated. This S-curve reflects the actual
progress of the project to date, and may be compared with the Baseline
and Target S-curves to determine how the project is progressing. During
the project, the Actual S-curve will terminate at the Cut Off Date. This
is the date the Production Schedule was last updated. At the completion
of the project, the Actual S-curve will meet the Target S-curve.
Value and Percentage S-curves
S-curves may be graphed as absolute values (i.e. Man Hours or Costs)
versus Time, or as percentage values versus Time. Value S-curves are
useful for determining Man Hours or Costs expended to date, and Man
Hours or Costs to complete. Percentage S-curves are useful for
calculating the project's actual percentage complete against target and
baseline percentage complete, and for calculating the project's
percentage growth (or contraction).