Resource Consumption / type of s curve details




Man Hours versus Time S-curve

The Man Hours versus Time S-curve is appropriate for projects that are labor intensive. It shows cumulative man hours expended over time for the duration of the project. As man-hours are a product of manpower and working hours, these may be adjusted together or individually in an attempt to keep the project on schedule. Projects may require additional man-hours to finish on time due to low productivity, delays and disruptions, rework, variations, etc.

Costs versus Time S-curve

The Costs versus Time S-curve is appropriate for projects that contain labor and non-labor (e.g. material supply / hire / subcontract) tasks. It shows cumulative costs expended over time for the duration of the project, and may be used to assist in the calculation of the project's cash flow, and cost to complete.

Baseline S-curve

Prior to project commencement, a schedule is prepared outlining the proposed allocation of resources and the timing of tasks necessary to complete the project within a set time frame and budget. This schedule is referred to as the Baseline Schedule. From this schedule, a Baseline S-curve is generated. This S-curve reflects the planned progress of the project. If the project requirements change prior to commencement (e.g. change of scope, delayed start), the Baseline Schedule may require revision to reflect the changed requirements.

Target S-curve

Following project commencement, modification of the Baseline Schedule is usually required. Changes are continually made to the Production Schedule (which is originally the same as the Baseline Schedule). The production schedule reflects the actual progress of the project to date, and any revisions made to tasks yet to commence or not yet completed. From this schedule, a Target S-curve may be generated. This S-curve reflects the ideal progress of the project if all tasks are completed as currently scheduled. In an ideal world, the Target S-curve will meet the Baseline S-curve at the end of the project (On Time, On Budget) or finish below and to the left of the Baseline S-curve (Early, Under Budget). In reality, it is not uncommon for the Target S-curve to finish above and to the right of the Baseline S-curve (Late, Over Budget).

Actual S-curve

The production schedule is updated on a regular basis throughout the duration of the project. These updates include the revision of percentage complete for each task to date. Using this information, an Actual S-curve may be generated. This S-curve reflects the actual progress of the project to date, and may be compared with the Baseline and Target S-curves to determine how the project is progressing. During the project, the Actual S-curve will terminate at the Cut Off Date. This is the date the Production Schedule was last updated. At the completion of the project, the Actual S-curve will meet the Target S-curve.

Value and Percentage S-curves

S-curves may be graphed as absolute values (i.e. Man Hours or Costs) versus Time, or as percentage values versus Time. Value S-curves are useful for determining Man Hours or Costs expended to date, and Man Hours or Costs to complete. Percentage S-curves are useful for calculating the project's actual percentage complete against target and baseline percentage complete, and for calculating the project's percentage growth (or contraction).